About the project:
Capital Park, CamLIFE is a dynamic campus for life science and innovation in Cambridge. This 42-acre campus provides approximately 245,000 square feet of innovation-focused workspace that is home to a dozen companies from sectors including fintech, agetch and biotech, through to patent law and the NHS.
Towards the end of 2024, Taunton Fabrications were awarded the contract to design, manufacture and install three sets of feature stairs. The 3 feature staircases combined fabricated structural steelwork with high-end finishing elements including vertical timber battens, timber handrails and integrated LED lighting to create a warm, contemporary aesthetic throughout the development.
From the outset, close collaboration between our design team, Wates and the wider project team was essential to ensure the complex architectural interfaces were successfully delivered. The combination of structural steelwork, timber finishes and integrated lighting required careful detailing to achieve the clean visual appearance intended by the architect while maintaining practical installation tolerances. As part of the collaborative process, we hosted key project stakeholders – including Wates Construction, Gensler, and Perkins & Will – at our state-of-the-art workshop facilities in Taunton. During this visit, the team was able to view and provide feedback on a controlled sample, ensuring the design and construction met the rigorous standards required for the project. Using detailed 3D modelling and early-stage coordination, the stair packages were developed to simplify installation and reduce clashes during the fit-out phase.

Collaboration at the heart of design
As part of the collaborative process, we hosted key project stakeholders – including Wates Construction, Gensler, and Perkins & Will – at our state-of-the-art workshop facilities in Taunton. During this visit, the team was able to view and provide feedback on a controlled sample, ensuring the design and construction met the rigorous standards required for the project.
Using detailed 3D modelling and early-stage coordination, the stair packages were developed to simplify installation and reduce clashes during the fit-out phase.
As always the stairs were fabricated in house and pre-assembled in our dedicated off-site build workshop and delivered to site, helping improve programme efficiency and ensuring consistency across all three stair installations which was especially important due to working alongside The Light Lab for the timber and lighting finishes.
The project required close coordination between all parties to successfully integrate the architectural steelwork, timber finishes and specialist lighting elements into a seamless final installation. The Light Lab’s bespoke LED handrail system, Glowrail, was specified for the Camlife Research Laboratories development in Cambridge, spanning Buildings 1, 2 and 3. Working to the original lighting design by 18 Degrees, who delivered the overall scheme, alongside interior design by Gensler. Designed to complement the contemporary architectural detailing throughout the new research facility, the Glowrail system was fabricated in a rich American walnut finish with custom powder-coated brackets, carefully coordinated to integrate seamlessly with the staircase design and surrounding materials. The installation incorporated multiple fixing methods across a range of substrates, including bespoke timber panelling and vertical timber slat battens, requiring close coordination between trades to achieve a refined, high-end finish.
Thomas Brothers Joinery, who are a trusted sub-contractor of ours, supplied these complimenting timber elements. The completed result delivers both functional architectural lighting and a warm, elegant visual feature that enhances the overall interior environment of the Camlife laboratories.
Images used © The Light Lab
Capital Park was a great example of what can be achieved when the right teams are involved early and work together properly. The feature stairs had a lot of interfaces to get right, from the structural steelwork through to the timber battens, handrails and integrated lighting, so communication and coordination with Wates, The Light Lab and the wider supply and design team was key.
The Light Lab were great to work with throughout the project. Their clear and timely communication helped keep everything running smoothly, ensuring the lighting and handrail details were properly coordinated with our steelwork, fixing arrangements and the surrounding timber finishes without compromising the final look.
By developing the details through 3D modelling, pre-assembling the stairs in our off-site build workshop and working closely with the specialist finishing trades, we were able to deliver a package that went together well on site and achieved the high-end architectural finish the project demanded.
Dave Baverstock, Director of Contracts