Project details:

Contractor:

Kier Group

Architects:

Roberts Limbrick

Architectural elements:

Balustrading, Steel Stairs, Handrails

About the project:

The overall project was a £45 million scheme involving both new build and refurbishment work, aiming to deliver high-quality, fit-for-purpose facilities within tight cost and programme constraints. From the outset, the scheme presented significant challenges: the redevelopment had to be fitted around live operations and a fixed events calendar.

Our package covered the design, fabrication and installation of bespoke balustrades, handrails and structural steel staircases across the new facilities. Attention to detail was essential, with every element required to combine durability and compliance with the visual standards expected at such a high-profile venue. The balustrades and handrails were designed to provide both safety and aesthetic value, complementing the architectural style of the new grandstand and hospitality areas.

One of the most pressing constraints was the short programme and the need to maintain spectator access throughout construction. Strong design integration and early collaboration were central to our work and from the beginning, we engaged closely with Kier, the architect and other specialist trades to ensure our balustrading, handrails and stair packages were fully coordinated. This proactive approach helped to minimise rework, reduce waste and keep the project moving to programme. By taking part in regular workshops and design reviews, we were able to resolve details early and deliver a consistently high-quality finish across all of our installations.

Environmental and sustainability measures were an important part of the project. During construction, Kier was recognised with the Gloucestershire Green Business Award, highlighting the commitment to reducing environmental impact both throughout the build and in the ongoing operation of the facilities.

This project was completed in 2015 and our balustrading, handrails and stair installations continue to serve thousands of visitors each year, offering robust performance, safety assurance and a finish in keeping with the prestige of Cheltenham Racecourse.

“Working with Kier on Cheltenham Racecourse was a great example of collaboration in practice. With such a high-profile venue and tight programme, coordination was crucial. By working closely with Kier’s team we were able to plan effectively, resolve details early and deliver our balustrading, handrails and stair installations to the quality expected at a venue of this prestige. Being there for the grand opening and seeing Princess Anne attend the ceremony, was a proud moment for everyone involved.”
Lynsay Brown, Managing Director

Images used © Taunton Fabrications